MiCiM have achieved PC on the first phase of DUB 4 the construction of a data centre building in Dublin, the project also included a central administration building and 4 x 3.84Mw IT data halls. This is a 2 storey build with the data halls...

MiCiM achieved PC in August for the Cyxtera LHR1-B Data Centre in Slough. The project consisted of upgrading existing data hall by 1.5 MW. Suppling and installing major plant including; Generators, SCRs, TXs, UPS’s, STS’s, PDU’s, Chillers, CRAH’s alongside the construction of a new extension to...

Some of our team have recently completed internal auditing training through our ISO accreditor ISOQSL Ltd, which has enabled us to make sure all of our processes have been implemented on all of our projects. We strongly rely on our staff applying the integrated management...